FS-2016-05

Service Bulletin Details

Public Details for: FS-2016-05

This field service bulletin provides new information from borg warner (delco) revising the maintenance procedure for starter b+ cable maintenance and torque values.


- 2016 - 2015 - 2014 - 2013 - 2012 - 2011 - 2010 - 2009 - 2008 - 2007 - 2006 - 2005 - 2004 - 2003 - 2002 - 2001 - 2000 - 1999 - 1998 - 1997 -

Number:
FS-2016-05
Date:__September 14, 2016
Model:
Diesel, CNG & BAE Hybrids With Starters
Model Years:
1997 - 2016
Subject:
Approved:
Robert L. Birdwell, Executive Director
Quality Control & Field Service
Starter B+ Cable & Stud Maintenance
Based on new information provided by Borg Warner, (Delco), we are revising the Starter
Maintenance procedure B+ cable maintenance and torque values.
FIELD
SERVICE
BULLETIN
You should follow the procedure below at 36,000 miles or once a year:
A.
Inspect solenoid cap for damage or cracks.
B.
Verify torque of outer nut at 20-25 ft lbs.
C.
Re-coating of the stud with Kopr-Shield or any other anti-corrosion substance is optional,
but if the B+ cable nut (outer nut) is removed, the inner nut should be held with a backing
wrench, or re-torqued to 15-20 ft lbs).
RLB:rlb
Gillig, LLC
25800 Clawiter Road
Hayward, CA 94545
(800) 735-1500
(510) 785-1500
[email protected]


© dot.report 2024

Use of this information constitutes acceptance for use in an AS IS condition. There are NO warranties, implied or otherwise, with regard to this information or its use. Any use of this information is at the user's risk. It is the responsibility of user to evaluate the accuracy, completeness or usefulness of any information, opinion, advice or other content. EACH USER WILL BE SOLELY RESPONSIBLE FOR ANY consequences of his or her direct or indirect use of this web site. ALL WARRANTIES OF ANY KIND ARE EXPRESSLY DISCLAIMED. This site will NOT BE LIABLE FOR ANY DIRECT, INDIRECT or any other kind of loss.